skip to main content

Amazon secures planning permission for three new data centres

(Stock image) The Council has granted planning permission despite opposition.
(Stock image) The Council has granted planning permission despite opposition.

Amazon Web Services (AWS) has secured planning permission for contentious plans to construct three new data centres in north Dublin.

This follows Fingal County Council giving the go-ahead to AWS firm, Universal Developers LLC for the three new data centre buildings with a combined power load of 73MW for the AWS data centre campus on a 65 acre land-holding at Cruiserath Road, Dublin 15.

In addition to the three granted planning permission, one AWS data centre is already operational at the campus while construction work continues on two others.

The council has granted planning permission despite opposition from Friends of the Earth, Not Here Not Anywhere, Gluaiseacht and others.

On behalf of Gluaiseacht, Eoin O Leidhin called on the council to reject the project claiming that "this project will lead to increased emissions in Ireland".

Head of Policy at Friends of the Earth (FOTE), Jerry Mac Evilly told the council that it should refuse planning permission as FOTE "remains concerned that the proposed development represents a serious risk of carbon lock-in".

However, in granting a seven-year planning permission, the council concluded that the construction of the three data centres would be consistent with European and Government policy concerning the development of digital infrastructure.

The council concluded that the project would not, in itself or taken cumulatively with other developments have a detrimental direct or indirect impact on the environment.

The planning authority has included a condition that prior to the operation of the data centres, that AWS have in place a Corporate Purchase Power Agreement (CPPA), which demonstrates that the energy consumed by the data centres is matched by new AWS renewable energy generation.

The council has stated that the new renewable energy projects shall be located in Ireland and the amount of electricity generated by the renewable energy projects shall be equal to or greater than the electricity requirements of the data centres in operation at any given time.

In its 69-page planner's report recommending that planning permission be granted, the Council concluded that the proposals by the AWS firm "demonstrate a clear pathway to decarbonise and provide a net zero data services, in terms of the targets set for the proposed development".

Planning consultant for the AWS firm John Spain told the council that "the proposed development does not entail a new request for power because it has an existing connection agreement" and will be supplied power by an existing transmission system.

Mr Spain stated that the existing connection agreement provides for eight incremental increases in power supply to the site, commencing in 2022 and completing in 2029.

A spokesman for AWS said: "The proposed development represents a significant investment that will create additional direct, indirect and induced economic and employment benefits, in addition to those that have already been generated by AWS.

"As such, it is fully consistent with the Government's preference, as set out in the Government Statement on the Role of Data Centres, for data centres to be associated with strong economic activity and employment."

The chief executive of Friends of the Earth, Oisín Coghlan, said the application for the three data centres amounts to 73 megawatts of power.

We need your consent to load this rte-player contentWe use rte-player to manage extra content that can set cookies on your device and collect data about your activity. Please review their details and accept them to load the content.Manage Preferences

Speaking on RTÉ's Morning Ireland, he said: "That might not mean much to most of us, but the Mount Lucas Wind Farm, which is 101 wind turbines, is 84 megabytes capacity. So that's at full capacity.

"We would barely just cover this. We're planning to bring Tarbert back online this winter, running oil, because of the emergency concerns we have about keeping the power grid stable and how to keep the lights on.

"And that's 150 megawatts, so half of target will be dedicated to keeping these data centers going rather than keeping our lights going," he added.